Led by Diellza Nika Hyseni and Mentor Nika · Updated 31 October 2026

Work out the CPR Part 47 deadlines from the dates you have: commencing detailed assessment, Points of Dispute, default costs certificates, Replies, requesting a hearing, provisional assessment and the certificates. Days are counted as the rules require, with bank holidays, court office closures and deemed service built in. Free, from DMD Costs, law costs draftsmen in Westhoughton, Bolton.

Fill in any dates you have. Each one adds the deadlines that run from it.

The costs order
The date of the judgment, order or other determination
Notice of commencement
The date it counts as served under CPR 6.26
Points of Dispute
The date it counts as served under CPR 6.26
Later stages
When the notice and Precedent G arrived
Default, interim or final, stating the amount

Your deadlines

Nothing yet

Your timetable builds here as you add dates, with each deadline, its rule and the latest day to serve.

Points of Dispute in, or a deadline close? We work for solicitor firms: our law costs draftsmen draw the bill, answer Points of Dispute with Replies and negotiate the costs to settlement. The fee is fixed and agreed before any work begins.

Send us the file

The calculator applies the default periods in the Civil Procedure Rules as they stood on 23 October 2026, with England and Wales bank holidays to 2028. Time can be varied by written agreement (CPR 2.11) or by the court, and an order may set its own dates, so check the rules, any order and any agreement before relying on a date. It is a guide, not legal advice, and it does not cover legal aid, Solicitors Act or fixed costs determination procedures (for a solicitor’s bill to its own client, use the Solicitors Act assessment checker). It assumes service within England and Wales: where a notice of commencement is served elsewhere, including in Scotland or Northern Ireland, Points of Dispute are due by the date inserted in the notice (PD 47 para 5.4), and business days follow the bank holidays where service takes place (CPR 6.2(a)).

Example: made-up details, fixed dates

Worked example: the deadlines after a costs order of 15 September 2026

A judgment with an order for costs is given on Tuesday 15 September 2026, and the notice of commencement and the bill are deemed served on the paying party on Wednesday 21 October 2026.

Points of Dispute are due by Wednesday 11 November 2026, 21 days after service of the notice of commencement (CPR 47.9(2)); if none have been served by then, a default costs certificate can be requested from Thursday 12 November 2026 (CPR 47.9(4) and 47.11; PD 47 para 10.1); the 3 months for commencing detailed assessment run from the judgment to Tuesday 15 December 2026 (CPR 47.6 and 47.7); and where Points of Dispute are served, a detailed assessment hearing must be requested by Monday 15 March 2027, 3 months after the end of the period for commencing (CPR 47.14(1) and 47.15).

A default costs certificate cannot be issued if any party serves Points of Dispute before it is issued, even late (CPR 47.9(5)).

Entered in the tool

The costs order
Judgment or order, Tuesday 15 September 2026
Notice of commencement, deemed date of service
Wednesday 21 October 2026
The timetable on these dates
DeadlineDateRuleTo be deemed served in time
Points of Dispute dueWednesday 11 November 2026CPR 47.9(2)Email before 4.30pm on Wednesday 11 November 2026, or first class post by Monday 9 November 2026 (CPR 6.26)
Earliest request for a default costs certificate (N254)Thursday 12 November 2026CPR 47.9(4) and 47.11; PD 47 para 10.1Filed at court, not served
Commence detailed assessment (N252)Tuesday 15 December 2026CPR 47.6 and 47.7Email before 4.30pm on Tuesday 15 December 2026, or first class post by Sunday 13 December 2026 (CPR 6.26)
Request a detailed assessment hearing (N258)Monday 15 March 2027CPR 47.14(1) and 47.15Filed at court, not served
Points to note
  • Points of Dispute due: time can be extended by written agreement or by the court (PD 47 para 8.1; CPR 2.11).
  • Commence detailed assessment: if it is late, the paying party can apply for an order requiring commencement by a set date on pain of losing costs; without that, the court may disallow interest (CPR 47.8).
  • Request a detailed assessment hearing: counted from the end of the CPR 47.7 period. If the court directed a different period for commencing, count from the end of that period instead; an agreed extension may not move this date (CPR 47.14(1)).

Worked out by the detailed assessment deadline calculator above, with the rules as they stood on . Try it with your own details. A guide, not legal advice.

Video · 0:50

Detailed assessment deadlines: the four dates in CPR Part 47

More short videos like this one, each with its transcript, are on our costs explainer videos page.

Transcript

You have a costs order, and the costs are not agreed. Detailed assessment has four deadlines, and missing one can cost money. Three months from the order to start detailed assessment, under rule 47.7. Twenty-one days for the paying party's points of dispute, under rule 47.9. Twenty-one days for replies, under rule 47.13. And three months, from the end of the period for starting, to request a hearing, under rule 47.14. Start late, and the court can disallow interest on the costs. If the paying party applies, the court can set a deadline and disallow costs if it is missed. That is rule 47.8. DMD Costs' free detailed assessment deadline calculator works out every date for you, at dmdcosts.co.uk.

The narration is a synthetic voice. Watch on YouTube.

Key points

  • DMD Costs’ detailed assessment deadline calculator is a free online tool that works out the CPR Part 47 timetable from the dates you have: commencement, Points of Dispute, the default costs certificate, Replies, the request for a hearing, provisional assessment and payment.
  • Detailed assessment is commenced by serving the notice of commencement (Form N252) and the bill within 3 months after the judgment, order or other event giving the right to costs (CPR 47.6 and 47.7).
  • Points of Dispute are due 21 days after service of the notice of commencement (CPR 47.9(2)). If none are served in time, the receiving party may request a default costs certificate on Form N254 (CPR 47.9(4)).
  • Where Points of Dispute are served, the request for a detailed assessment hearing (Form N258) is due within 3 months after the end of the period for commencing (CPR 47.14(1)).
  • Days are counted under CPR 2.8, with court office closures under CPR 2.8(5) and Practice Direction 2A, and documents other than a claim form are deemed served under CPR 6.26.

The deadlines at a glance

Detailed assessment timeline: notice of commencement within 3 months, Points of Dispute in 21 days, Reply in 21 days, then request an assessment

Detailed assessment timeline in England and Wales: the receiving party serves its notice of commencement (Form N252) and bill within 3 months of the judgment, order or other event giving the right to costs (CPR 47.7). The paying party has 21 days to serve Points of Dispute (CPR 47.9(2)), failing which a default costs certificate can be requested (CPR 47.9(4)). A Reply may follow within 21 days (CPR 47.13), and an assessment is requested on Form N258 within 3 months after the period for starting ends (CPR 47.14). Bills of £75,000 or less are normally assessed provisionally, on paper (CPR 47.15).

Free to reuse under CC BY 4.0: credit “DMD Costs (dmdcosts.co.uk)” and link to this page. Download the PNG.

Text version of this diagram

From the right to costs to the final costs certificate, with the deadlines in the rules.

  1. Start: The right to costs. A judgment, order or other event entitles a party to its costs.
  2. Within 3 months: Notice of commencement and bill. The receiving party serves Form N252 with its bill of costs. Starting late is a breach: the paying party can ask for a deadline on pain of losing costs; otherwise interest may be disallowed (CPR 47.6, 47.7, 47.8).
  3. 21 days after service: Points of Dispute. The paying party serves its Points of Dispute (CPR 47.9(2)).
    • None in time? The receiving party can request a default costs certificate on Form N254, unless late Points of Dispute are served before it is issued (CPR 47.9(4) and (5)).
  4. 21 days after Points of Dispute: Reply (optional). The receiving party may serve a Reply to the Points of Dispute (CPR 47.13).
  5. 3 months after the start deadline: Request an assessment. If the costs are not agreed, the receiving party files Form N258 within 3 months after the period for starting detailed assessment ends (CPR 47.14(1)).
    • Bills of £75,000 or less are normally assessed provisionally, on paper. A challenge must be made within 21 days of receiving the court’s notice; if it goes no further, the costs of the assessment, apart from drafting the bill, are capped at £1,500 plus VAT and court fees (CPR 47.15, PD 47 para 14.1).
  6. After the assessment: Final costs certificate. After a hearing, the completed bill is filed within 14 days. The court then issues the final costs certificate; the costs are payable within 14 days of it (CPR 47.17(2), 44.7).
    • After a provisional assessment, the parties instead agree the total within 14 days of receiving the court’s decision (PD 47 para 14.4(2)).

Rules checked 27 October 2026.

StepTime limitRule
Commence detailed assessment: serve the notice of commencement (N252) and the bill3 months after the judgment, order or other event giving the right to costsCPR 47.6 and 47.7
Serve Points of Dispute21 days after service of the notice of commencementCPR 47.9(2)
Request a default costs certificate (N254)Once those 21 days have expired with no Points of Dispute servedCPR 47.9(4)
Serve Replies (optional)21 days after service of the Points of DisputeCPR 47.13(2)
Request a detailed assessment hearing (N258)3 months after the end of the period for commencing detailed assessmentCPR 47.14(1)
Agree the sum due after a provisional assessment14 days after receipt of the provisionally assessed Precedent GPD 47 para 14.4(2)
Request an oral hearing after a provisional assessmentFile and serve on all other parties within 21 days of receipt of the notice of provisional assessmentCPR 47.15(7)
File the papers in support of the billNot more than 14 and not less than 7 days before the hearingPD 47 para 13.11
File the completed bill14 days after the end of the detailed assessment hearingCPR 47.17(2)
Pay the costs14 days after the certificate stating the amountCPR 44.7(1)(b)

To fill in the forms themselves, use our free builders for the N252 notice of commencement, the N254 request for a default costs certificate and the N258 request for provisional or detailed assessment. They work from these same dates. For what each step involves, see our guide to detailed assessment step by step and our guide to Points of Dispute and Replies.

Appealing a detailed assessment decision

An appeal from an authorised court officer in detailed assessment proceedings goes to a costs judge or a District Judge of the High Court as a re-hearing, and needs no permission: the appellant’s notice, which should be in Form N161, must be filed within 21 days after the date of the decision (CPR 47.21 to 47.24; PD 47 paras 20.2 to 20.4). Any other appeal arising out of detailed assessment, such as one from a costs judge or a District Judge, follows Part 52 and needs permission (PD 47 para 20.1; CPR 52.3). The appeal checker gives the appeal court and the last day for the notice, and the free N161 builder fills in the appellant’s notice.

How the dates are counted

Days are clear days

A period expressed in days is counted in clear days: the day of the event that starts it is not included (CPR 2.8(2) and (3)). Points of Dispute due 21 days after a notice served on Monday 19 October 2026 are therefore due by Monday 9 November 2026. Periods of 5 days or less also leave out weekends, bank holidays, Christmas Day and Good Friday (CPR 2.8(4)), though none of the Part 47 periods is that short.

Months are calendar months

Three months after 18 October is 18 January: a period of months ends on the corresponding date. Where the later month has no such date, it ends on the last day of that month, so three months after 30 November is 28 February, or 29 February in a leap year (Dodds v Walker, House of Lords, 1981). The period for requesting a hearing is counted from the end of the period for commencing, which can differ by a day or two from six months after the order.

When the court office is closed

Where the last day for doing something at the court office, such as filing a request, falls on a day the office is closed, filing on the next day it is open is in time (CPR 2.8(5)). Court offices are closed at weekends, on bank holidays, Good Friday and Christmas Day, and on one further day over Christmas set by a table in Practice Direction 2A (24 December in 2026 and 2027), and on any other day the Lord Chancellor directs. That extension does not apply to serving documents on the other side.

Which court office a detailed assessment request goes to depends on where the case was dealt with (CPR 47.4; PD 47 paras 4.1 and 4.2). Our city-by-city guide names the County Court hearing centre for 30 cities, and the London centres whose requests for a hearing go to the Senior Courts Costs Office.

Deemed service

Documents other than a claim form are deemed served under CPR 6.26. A document sent by email, sent by fax, delivered to a permitted address or served personally before 4.30pm on a business day is deemed served that day; otherwise it is deemed served on the next business day. A document sent by first class post or document exchange is deemed served on the second day after posting if that is a business day, or else on the next business day. Email can be used only where the party to be served, or its solicitor, has previously indicated in writing that it will accept service by email and given the address to use; an email address on a solicitor’s letterhead counts only where it says it may be used for service (PD 6A para 4.1).

For the forms themselves, see our costs forms and precedents guide; the terms are defined in the legal costs glossary. For a summary assessment at a hearing, our N260 statement of costs builder fills in the statement of costs. Earlier in a claim, the deemed service calculator works out service and the defence; once the costs are fixed, the interest on costs calculator works out the 8% interest. For any other time limit under the rules, use the CPR deadline calculator. Every stage is explained on our costs help page.

Sources

Frequently asked questions

Yes. It is completely free, with no sign-up, no paywall and no limit. It runs in your browser, and nothing you type is sent to DMD Costs. It is a guide to the rules, not legal advice.
21 days after the date of service of the notice of commencement (CPR 47.9(2)). The day of service is not counted, so if the notice is served on Monday 19 October 2026, Points of Dispute are due by Monday 9 November 2026. The time can be extended by written agreement or by the court (PD 47 para 8.1). Where the notice is served outside England and Wales, including in Scotland or Northern Ireland, Points of Dispute are due by the date inserted in the notice instead (PD 47 para 5.4).
Once the period for serving Points of Dispute has expired and no Points of Dispute have been served (CPR 47.9(4)). The request is made on Form N254. The court cannot issue the certificate if any party serves Points of Dispute before it is issued, even late (CPR 47.9(5)).
Three months after the date of the judgment, order or other event giving the right to costs (CPR 47.7). If commencement is late, the paying party can apply for an order requiring it by a set date on pain of losing costs; without that, the court may disallow interest (CPR 47.8).
Where Points of Dispute have been served, within 3 months of the end of the period for commencing detailed assessment (CPR 47.14(1)), so about six months after the costs order when the default periods apply. The request is made on Form N258.
For an act at the court office, such as filing Form N258, CPR 2.8(5) makes it in time if done on the next day the court office is open. There is no such extension for serving documents on the other side: a document served on a day that is not a business day is deemed served on a later day (CPR 6.26), so it has to be sent early enough to be deemed served in time.
No. It applies the default periods in the Civil Procedure Rules. Where time has been varied by written agreement (CPR 2.11) or by the court, the dates in the agreement or order apply instead. One caution: the time for requesting a hearing is counted from the period for commencing as set by CPR 47.7 or by a court direction (CPR 47.14(1)), so an agreed extension of the time for commencing may not move it.

Deadlines in hand, but the bill still to draw?