Request a fixed-fee quote →
07900 008720info@dmdcosts.co.ukClient portal
Home / Costs help / Payment on account of costs calculator
Free tool

Payment on Account of Costs Calculator

Led by Diellza Nika Hyseni and Mentor Nika · Updated 18 November 2026

Test a payment on account of costs under CPR 44.2(8): the sum at the percentages you choose, with incurred and budgeted costs apart, the costs order’s share and earlier payments taken off, the date it must be paid, and what courts have ordered in the cases.

  • Free, with no sign-up
  • No percentage presented as the rule
  • Every case with its facts
  • Nothing leaves your browser

For an order to pay costs subject to detailed assessment (CPR 44.2(8)). Enter the costs claimed and choose the percentages to test: no rule fixes one, so the calculator does not pick one for you. The case table below the calculator shows what courts have ordered, and why.

Where the right to costs comes from
Costs are payable under
Basis of assessment
The costs claimed
Was there a costs management order (an approved or agreed budget)?
A scenario: for example a phase covered by another order, or work said to be outside the order.
The costs order and earlier payments
Such as 60 for an order to pay 60% of the costs. Leave blank for all of them.
The percentages to test
When it must be paid

The rules and judgments were read on 18 November 2026. The calculator does arithmetic on the figures and percentages you enter; the court decides a reasonable sum on the evidence in each case. It is a guide, not legal advice.

Key points

  • CPR 44.2(8): “Where the court orders a party to pay costs subject to detailed assessment, it will order that party to pay a reasonable sum on account of costs, unless there is good reason not to do so.”
  • No rule fixes a percentage. A reasonable sum is often an estimate of the likely recovery on detailed assessment, less a margin for error (Excalibur Ventures v Texas Keystone [2015] EWHC 566 (Comm) at [23]); the court in Cubic v TfL [2026] EWHC 211 (TCC) accepted that there is no fixed percentage ([11] and [12]).
  • In the cases below the stated shares run from 50% (of the costs recoverable under a 60% order, in Abbott) to 90% (of approved budgeted costs, in Thomas Pink and Lawrence). Measured against the costs claimed the spread is wider: about 46% in Cleveland Potash and, on our arithmetic, about 26% of the gross costs in Abbott for the new order (about 40% counting the £1,355,000 already paid on account). The base differs from case to case, so the percentages are not comparable without the facts.
  • With a costs management order, the court approves the budgeted (estimated) costs but not the incurred costs (CPR 3.17(3)(a)), and on a standard basis assessment it will not depart from the budgeted figures without good reason (CPR 3.18). Courts have therefore treated budgeted costs as the more robust figure and kept a bigger margin on incurred costs (Car-Wizard [2026] EWHC 2177 (Ch) at [45] and [46], an indemnity costs case).
  • The sum is payable within 14 days of the order unless the court sets another date (CPR 44.7(1)); later, after a request for a detailed assessment hearing, the court can issue an interim costs certificate (CPR 47.16).
  • Where costs follow acceptance of a Part 36 offer within the relevant period, CPR 44.2(8) does not apply, because no court has ordered costs (Finnegan v Spiers [2018] EWHC 3064 (Ch) at [31]).

The rule: CPR 44.2(8)

“Where the court orders a party to pay costs subject to detailed assessment, it will order that party to pay a reasonable sum on account of costs, unless there is good reason not to do so.”

The rule applies when the court makes an order for costs to be assessed by detailed assessment. Where costs are assessed summarily, the court fixes the figure there and then. Once the receiving party has filed a request for a detailed assessment hearing, the court can also issue an interim costs certificate (CPR 47.16), and when it sets aside a default costs certificate it can attach conditions and order a payment on account (PD 47 para 11.3). For the wider question of interim payments of damages and costs, see our guide to interim payment percentages; for a worked example of the reasoning, our note on Cubic v TfL.

What courts have ordered

These are each court’s findings on its own evidence, not benchmarks. Read the “share” column with care: the percentage is of a different base in almost every case.

Payments on account of costs ordered under CPR 44.2(8), by case
CaseBasis and budgetCosts, sought and offeredOrderedShare, and of whatWhy
Cleveland Potash Ltd v Secretary of State for Business, Energy and Industrial Strategy [2026] EWHC 2781 (BP)
High Court, Master Kaye sitting as a Deputy High Court Judge, 30 October 2026 · our note
Standard. Not budgeted: a phase-by-phase scheduleCosts claimed £1,204,160.86; sought £700,000; the first respondent proposed a figure based on 30% ([153])£550,000 ([186])About 46% of the costs claimed (our arithmetic: the court set a sum, not a percentage)Costs and the sum sought on the high side, with phases that appeared to include irrecoverable costs, but 30% too low; £550,000 left substantial headroom ([185] to [187]).
Baroness Lawrence of Clarendon OBE and others v Associated Newspapers Ltd [2026] EWHC 2207 (KB)
High Court, Nicklin J, 21 August 2026 · our note
Indemnity. Costs managed: approved budgeted costs plus incurred pre-budget costsSought 90% of budgeted and 65% of pre-budget costs; the claimants accepted 90% of budgeted costs and offered 40% of pre-budget costs ([185] and [186])£9,544,355, by 28 August 2026 ([189] and [191])£4,669,127.10 (90% of approved budgeted costs, conceded) plus £4,875,228.24 (60% of incurred pre-budget costs), rounded down to the pound ([189])Exceptionally large costs justified a substantial margin on the pre-budget costs, but the indemnity basis supported more than the claimants offered ([188] and [189]).
Car-Wizard Ltd v Vixen Surface Treatments Ltd [2026] EWHC 2177 (Ch)
High Court, HHJ Paul Matthews sitting as a Judge of the High Court, 17 August 2026 · our note
Indemnity. Costs managed: budget estimated costs £146,668, budget incurred costs £148,244Costs order: 90% of the claimant’s costs ([35]); sought £236,000 (90% of estimated, 70% of incurred); the defendant suggested 50% ([46])£214,000 ([46])80% of the budget estimated costs and 65% of the budget incurred costs, with the 90% costs order folded into the choiceCosts on the indemnity basis throughout ([36] and [41]). The approved (estimated) figure is more robust than the incurred figure, which the court does not approve, so the margin on incurred costs is bigger ([45] and [46]).
Abbott and others v Ministry of Defence [2026] EWHC 2083 (KB)
High Court, Garnham J, with Master Brown as assessor, 7 August 2026 · our note
Standard. Common costs in group litigation; no signed draft bill or certified scheduleCommon costs £9,738,983.15, less £1,355,000 already paid on account; the claimants sought 65%, the Ministry suggested 36% ([73] and [74])£2,515,194.95 ([79])50% of the costs recoverable under a 60% costs order, after deducting the earlier payment: 50% × 60% × £8,383,983.15Real concerns about rates, hours, seniority, delegation and disbursements without certified figures; a broad-brush estimate with a margin of error; the paying party was good for the money and a further interim certificate was possible ([75] to [78]). The judge invited further submissions on the mathematics if the figures were not agreed ([80]), so the order of the steps is not settled.
Cubic Transportation Systems Ltd v Transport for London [2026] EWHC 211 (TCC)
Technology and Construction Court, Mr Roger ter Haar KC sitting as a Deputy High Court Judge, 5 February 2026 · our note
Not stated (standard by default, CPR 44.3(4)). Costs of an interim application (to lift the automatic suspension) and of an application for expeditionCosts claimed £1,201,444.75; sought £720,866.85; the paying party offered no more than £300,000 ([7] and [8])£720,866.85, the full sum sought ([14])60% of the costs claimedNo fixed percentage ([11] and [12]); high-value procurement, heavy evidence, the counsel teams, and the paying party’s own costs of £1,182,020.75 ([13]).
Harlequin Property (SVG) Ltd v Wilkins Kennedy [2016] EWHC 3233 (TCC)
Technology and Construction Court, Coulson J, 21 December 2016
Standard. No costs management ([48])Draft bill just over £5.1 million; costs order 60%; the paying party argued for 30% ([43], [44] and [49])£2 million, paid into court until further order ([50])Two thirds of the roughly £3 million recoverable under the 60% orderNo general rule of 40% to 50% of the bill; general parity with the paying party’s own £4.7 million costs gave confidence ([49]). The judge applied the Mars v TeKnowledge test (a figure he was confident would not exceed the assessed costs), the approach Excalibur declined to treat as the test ([22]).
Excalibur Ventures LLC v Texas Keystone Inc [2015] EWHC 566 (Comm)
Commercial Court, Christopher Clarke LJ, 3 February 2015
Indemnity. Not budgeted: litigation the judge called gargantuan; the paying parties were the funders of the losing claimantEarlier estimate of recovery on the indemnity basis: 85% of the costs claimed ([25])80% of the costs claimed ([25] and [28])80% of the costs claimed (the 85% estimate less a margin for error)A reasonable sum is often an estimate of the likely recovery less a margin for error ([23]); the factors at [24]; little risk in recovering any overpayment ([28]).
Thomas Pink Ltd v Victoria’s Secret UK Ltd [2014] EWHC 3258 (Ch)
High Court, Birss J, 31 July 2014
Not stated (standard by default, CPR 44.3(4)). Approved budget £678,009.10 ([51]); the claimant sought £644,829 ([52])The paying party suggested about £350,000 ([57])90% of £644,829.10, rounded up to the nearest thousand ([60]): about £581,000 on our arithmetic90% of £644,829.10, the costs to date claimed within the approved budgetAn approved budget will not be departed from without good reason, which has a very significant impact on the sum on account ([60]). The judge used the “irreducible minimum” approach ([58]), which Excalibur at [22] declined to treat as the test.

Two cases with almost the same costs claimed, about £1.2 million, show why the percentage is an output of the evidence: 60% in Cubic, and about 46% in Cleveland Potash, where the judge could point to specific costs that might not survive assessment. Our Cleveland Potash note goes through the phase-by-phase reasoning, and our Abbott note the figures behind the 50%.

How a reasonable sum is worked out

In Excalibur Ventures v Texas Keystone the court said that any sum will have to be an estimate, and that a reasonable sum would often be an estimate of the likely level of recovery subject to an appropriate margin for error, for example by taking the lowest figure in a likely range or deducting from a single estimate ([23]). It rejected the older “irreducible minimum” test as the criterion ([22]), and the courts in Cleveland Potash ([149]) and Lawrence ([186]) followed that approach. The calculator mirrors those steps:

  1. Start from the costs claimed: incurred and budgeted costs apart where there is a costs management order.
  2. Take off, as a scenario, any costs the paying party says cannot be recovered at all.
  3. Apply the costs order’s share, if it is for a percentage of the costs.
  4. Apply the percentages you want to test, which stand for the likely recovery less a margin.
  5. Take off any payment already made on account, from the costs first (as in Abbott) or from the result.

The factors the court weighs

  • Likely recovery. The level of the costs against the court’s provisional view of what is reasonable and proportionate (Cubic at [11]), and any costs that may not be recoverable at all, such as costs covered by another order (Cleveland Potash at [176]).
  • The information. The receiving party must give enough to make a safe order (Cleveland Potash at [152]). In Abbott the absence of a signed draft bill or certified schedule, with concerns about rates, hours, seniority, delegation and disbursements, led to 50% where 65% was sought ([75] and [78]).
  • The budget. On a standard basis assessment, approved or agreed budgeted costs are departed from only for good reason (CPR 3.18); incurred costs are not approved (CPR 3.17), so courts keep a bigger margin on them (Car-Wizard at [45]).
  • The basis of assessment. Indemnity costs supported higher sums in Excalibur ([25]) and Lawrence ([189]).
  • Comparisons and conduct. The paying party’s own costs can be informative (Cubic at [13]; Harlequin at [49]), and so can the way the case was run: in Excalibur, where the funders of the losing claimant were ordered to pay, the court bore in mind the work generated by the way the claimant and its solicitors conducted the litigation before and after trial ([25]).
  • Risk. Any difficulty in recovering the costs, the likelihood of an appeal, the parties’ means, how soon the assessment will be, and whether an overpayment could be recovered (Excalibur at [24] and [28]; Abbott at [77]).

When it must be paid, interest and what follows

A party must comply with an order for the payment of costs within 14 days of the date of the order if it states the amount, or by such other date as the court may specify (CPR 44.7). CPR 40.11 says the same of any order for the payment of an amount of money (including costs). After Part 36 acceptance, where no order on account is available, an interim costs certificate is payable within 14 days of the certificate (CPR 44.7(1)(b)). The calculator counts 14 days from the order or certificate, without moving a date that falls at a weekend or on a bank holiday. Interest on costs runs from the date of the order on the sum eventually found due; a payment on account, once made, reduces the exposure to interest (Cleveland Potash at [199]): our interest on costs calculator allows for payments on account. The detailed assessment deadline calculator covers the steps that follow, and the glossary has the definition of a payment on account.

Sources

Frequently asked questions

A sum the paying party must pay towards costs before they are assessed. Where the court orders a party to pay costs subject to detailed assessment, it will order that party to pay a reasonable sum on account of costs, unless there is good reason not to do so (CPR 44.2(8)). The burden of showing a good reason is on the paying party (Cleveland Potash [2026] EWHC 2781 (BP) at [146]).
Because no rule fixes one. In Cubic Transportation Systems v Transport for London [2026] EWHC 211 (TCC) the judge accepted that there is no fixed percentage, and that the amount depends on the costs claimed against the court’s provisional view of what is reasonable and proportionate, and on the quality of the information given ([11] and [12]). In Harlequin v Wilkins Kennedy [2016] EWHC 3233 (TCC) the court rejected a general rule of 40% to 50% of the bill ([49]).
Any sum is an estimate, because there has been no detailed assessment. A reasonable sum would often be an estimate of the likely level of recovery less an appropriate margin for error, for example the lowest figure in a likely range, or a deduction from a single estimate (Excalibur Ventures v Texas Keystone [2015] EWHC 566 (Comm) at [23]). It is not a search for an irreducible minimum (at [22]; Lawrence [2026] EWHC 2207 (KB) at [186]).
All relevant factors, including the likelihood of the costs being awarded in full or in part, any difficulty in recovering them, the likelihood of a successful appeal, the parties’ means, how soon the assessment will be, any delay, and whether the paying party could recover an overpayment (Excalibur [2015] EWHC 566 (Comm) at [24]). The receiving party must give enough information for a safe order; the paying party must identify the factors it relies on (Cleveland Potash [2026] EWHC 2781 (BP) at [152]).
On a standard basis assessment the court will not depart from approved or agreed budgeted costs without good reason (CPR 3.18), so budgeted costs are a robust base; the rule does not apply on the indemnity basis. In Thomas Pink v Victoria’s Secret [2014] EWHC 3258 (Ch) the court ordered 90% of the sum in the claimant’s budget ([60]). In two indemnity cases the courts still treated the approved figures as the firmer base: 90% of budgeted costs in Lawrence [2026] EWHC 2207 (KB) (conceded, [185] and [189]), and 80% of budgeted against 65% of incurred costs in Car-Wizard [2026] EWHC 2177 (Ch) ([45] and [46]).
It is a relevant factor, because on the indemnity basis doubts about reasonableness are resolved in the receiving party’s favour (CPR 44.3(3)). In Excalibur [2015] EWHC 566 (Comm) the court ordered 80% of the costs claimed on the indemnity basis ([25] and [28]); in Lawrence [2026] EWHC 2207 (KB) the indemnity basis supported 60% of pre-budget costs where the claimants offered 40% ([189]).
Courts have applied the order’s percentage first and then the share on account. In Abbott v Ministry of Defence [2026] EWHC 2083 (KB) the court took the earlier payment on account off the costs claimed, applied the 60% order and ordered 50% of the result, £2,515,194.95 ([79]). In Harlequin [2016] EWHC 3233 (TCC) it ordered two thirds of the roughly £3 million due under a 60% order ([50]). In Car-Wizard the judge instead reflected a 90% order in the percentages he chose ([46]).
Within 14 days of the order if it states the amount, unless the court specifies another date (CPR 44.7(1)(a) and (c)). CPR 40.11 says the same of any order for the payment of an amount of money (including costs). After Part 36 acceptance, an interim costs certificate is payable within 14 days of the certificate (CPR 44.7(1)(b) and 47.16(2)). Courts often set the date in the order: in Lawrence [2026] EWHC 2207 (KB) the payment was ordered by 28 August 2026 ([191]).
Not under CPR 44.2(8) where the offer is accepted within the relevant period: the costs order is only deemed, so the court has not ordered costs (Finnegan v Spiers [2018] EWHC 3064 (Ch) at [31] and [32]). The judge left open other cases, such as late acceptance, where Part 36 gives the court a discretion. Once a request for a detailed assessment hearing is filed, the court can issue an interim costs certificate (CPR 47.16).
After the receiving party has filed a request for a detailed assessment hearing, the court may issue an interim costs certificate for such sum as it considers appropriate (CPR 47.16(1)). It includes an order to pay unless the court orders otherwise (CPR 47.16(2)), is applied for under Part 23 (PD 47 para 15), and can be enforced like a judgment (PD 47 para 16.12).
No, but once paid it reduces the paying party’s exposure to interest (Cleveland Potash [2026] EWHC 2781 (BP) at [199]). Interest on costs runs from the date of the costs order on the sum eventually found due (Judgments Act 1838 and CPR 40.8; Cleveland Potash at [190] to [192]), unless the court orders a different date under CPR 44.2(6)(g); in Cleveland Potash it refused to defer it ([201]).
Yes. It is free, with no sign-up, and nothing you enter is sent to DMD Costs. It works out figures at the percentages you choose and the CPR 44.7 due date; the court decides the sum in each case.

Payment on account in issue?

We work mainly for claimant solicitor firms: we prepare the schedule or draft bill that shows the court what will survive assessment, answer the paying party’s points, and take the costs through detailed assessment. The fee is fixed and agreed before any work begins.